NEWS RELEASE · 7th December 2011
National Energy Board
Joint Review Panel for Enbridge Northern Gateway Project Issues Details for the First Portion of the Community Hearings

The Joint Review Panel (the Panel) conducting the review of the proposed Enbridge Northern Gateway Project has confirmed the following portions of the schedule for the community hearings. The Panel will hear all oral evidence from registered intervenors first. The schedule for the remaining locations will be released once venue availability and logistics have been confirmed.

Location Venue Date and Start Time

Kitimat, BC Riverlodge Recreation Center
654 Columbia Avenue West: 10 and 11 January 2012, starting at 9:00 a.m.

Terrace, BC Sportsplex
3320 Kalum Street: 12 January 2012, starting at 1:00 p.m.

Smithers, BC Hudson Bay Lodge and Convention Centre
3251 East Highway 16: 16 January 2012, starting at 9:00 a.m.

Burns Lake, BC Island Gospel Fellowship Church
810 Highway 35: 17 January 2012, starting at 1:00 p.m.

Prince George, BC Ramada Hotel Downtown
444 George Street: 18 January 2012, starting at 6:00 p.m.

Edmonton, AB Wingate Inn Edmonton West Hotel
18220 - 100th Avenue: 24, 25, 26, 27, 30 and 31 January 2012, starting at 9:00 a.m.

Fort St. James, BC Royal Canadian Legion, Branch no. 268
330 - 4th Avenue East: 2 February 2012, starting at 9:00 a.m.

Bella Bella, BC Heiltsuk Elders Building: 3 February 2012, starting at 6:30 p.m.;
4 February 2012, starting at 9:00 a.m.

Prince Rupert, BC North Coast Meeting and Convention Centre
240 - 1st Avenue West: 16, 17, 18, 20, 21, 22, 23 and 24 February 2012, starting at 9:00 a.m.

Masset, BC Howard Phillips Community Hall
1590 Cook Street: 28 February 2012, starting at 9:00 a.m.

Queen Charlotte City, BC, Queen Charlotte Community Hall
134 Bay Street: 29 February 2012, starting at 1:00 p.m.

Grande Prairie, AB Quality Hotel and Conference Centre
11201 - 100 Avenue: 26 March 2012, starting at 6:00 p.m.;
27 and 28 March 2012, starting at 9:00 a.m.

Courtenay, BC To be determined, 30 and 31 March and 2 and 3 April 2012, starting at 9:00 a.m.

Other locations where the venue availability and logistics have not yet been confirmed include: Klemtu, BC, Hartley Bay, BC, Kitkatla, BC and Bella Coola, BC.

After the Panel has heard all oral evidence, it will then hear oral statements and will follow this estimated schedule.

Estimated Time Frame Activity

-Late March - July 2012: Oral statements from registered participants who live in or near the proposed Project area.
-September - October 2012: Final hearings where the applicant, intervenors, government participants and the Panel will question those who have presented oral or written evidence.
-November 2012 - March 2013: Oral statements from registered participants who do not live in or near the proposed Project area (i.e. Kelowna, Port Hardy, Victoria, Vancouver, and Calgary).
-April 2013: Final argument from the applicant, intervenors and government participants.

This estimated schedule may change and is meant to be used only for planning purposes. Based on this projected schedule, the Panel would anticipate releasing the Environmental Assessment Report in the fall of 2013 and its final decision on the project around the end of 2013.

In order to accommodate the above schedule, an amendment to certain deadlines set out in the Hearing Order is required. These dates will be released shortly.

The proposed Northern Gateway project involves the construction of two 1,170 kilometre long pipelines running from Bruderheim, Alberta to Kitimat, British Columbia and the construction and operation of the Kitimat Marine Terminal.

For more information on the joint review process, please visit the Panel's website at www.gatewaypanel.review.gc.ca.